RicherFin · Sovereign Projects

Rwanda Emergency Connectivity Restoration Project — Rwanda

Alternative / official name: RECOR

Rwanda · Primarily affected areas of the Western and Northern provinces · Transport

Overview

The Rwanda Emergency Connectivity Restoration Project aims to restore road connections damaged by the May 2023 floods and landslides in a climate-resilient manner. These events severely affected the road network, particularly in the western and northern parts of the country, disrupting access to markets, schools, health centres and other socioeconomic infrastructure.

The programme mainly finances the targeted rehabilitation or reconstruction of damaged national roads, district roads and bridges. It also includes climate-resilience measures such as slope stabilisation, reforestation, improved drainage and reinforcement of vulnerable structures. The operational target covers approximately 380 km of roads, in addition to the affected structures.

The World Bank approved the project in April 2024 and it became effective on 25 July 2024. In the latest identified public progress report, dated 3 October 2025, works had begun on several national roads while district-road and bridge contracts were at different stages of award. The World Bank rated both progress toward the development objective and overall implementation progress Satisfactory.

Key project information

Official name
Rwanda-Emergency Connectivity Restoration Project
Acronym
RECOR
Status
Under implementation
Current phase
Implementation
Country
Rwanda
Location
Primarily affected areas of the Western and Northern provinces
Sector
Transport
Sub-sector
Roads and bridges
Project structure
Sovereign public financing / Investment Project Financing
Project ID
P504023
Total project cost
USD 93.68m
Financing secured
USD 93.68m
Documented financing gap
USD 0
Approval
25 Apr 2024
Effectiveness
25 Jul 2024
Expected closing
29 Sep 2028

Financing

The documented total project cost is USD 93.68 million. The financing plan comprises an USD 80.00 million International Development Association credit and USD 13.68 million of national public counterpart financing. World Bank financing documents report total financing of USD 93.68 million and no financing gap.

Total project cost
USD 93.68m
Financing secured
USD 93.68m
Financing gap
USD 0
Financing structure
IDA concessional credit + national public financing
IDA debt / credit
USD 80.00m