Overview

The Abidjan Urban Transport Project (PTUA) is an infrastructure programme intended to improve mobility across Greater Abidjan, reduce road congestion and strengthen urban traffic management. The component corresponding to AfDB project P-CI-D00-004 was approved in December 2016 and includes the Fourth Abidjan Bridge and its approaches, together with interventions on the road network and traffic-management systems.

The wider PTUA programme also comprises urban expressways, interchanges, junction upgrades and traffic-management equipment. African Development Bank documents distinguish the initial P-CI-D00-004 project from Phase 2, which is recorded separately as P-CI-D00-010. The financial data for these two operations are therefore not combined here.

The latest available implementation assessment for P-CI-D00-004 is based on a mission conducted from 29 September to 15 October 2025 and a report dated 24 November 2025. The Bank continues to list the project as ongoing. In August 2026, Côte d'Ivoire's infrastructure ministry still presented PTUA as a structuring urban-mobility programme with delivered works and further implementation prospects.

Key project information

Official name
Abidjan Urban Transport Project
Status
Ongoing
Current phase
Implementation
Country
Côte d'Ivoire
Location
Greater Abidjan
Sector
Transport
Sub-sector
Urban transport · road infrastructure
Project structure
Sovereign public investment
RicherFin project ID
0159a86a-d1b8-4f52-a86a-ef2f61f2c276
AfDB project ID
P-CI-D00-004
Project cost · P-CI-D00-004
€294.53 million
Identified financing
€294.53 million in the published financing plan
Financing sought
Not documented
Approval date
16 Dec 2016

Financing

The latest available implementation report for P-CI-D00-004 presents a total financing plan of €294.53 million, comprising African Development Bank financing, Global Environment Facility financing and a public contribution from Côte d'Ivoire.

Total project cost
€294.53 million
Identified financing
€294.53 million
Financing sought
Not documented
Financing gap
No gap explicitly documented in the published financing plan
Financing structure
Sovereign loan · grant · public contribution