The Sierra Leone Rice Systems Capacity Strengthening Project is a US$2.80 million capacity-building and climate-smart agriculture programme designed to increase adoption of sustainable rice-production practices among smallholder farmers in four districts. It uses South-South knowledge exchange, including technical cooperation with Viet Nam, to strengthen production, extension, research and farmer-support systems. The latest World Bank documentation targets 12,000 rice farmers.
Activities include demonstration and learning plots, training in climate-smart rice technologies, capacity development for extension and research personnel, support to farmer organisations, and assistance to youth- and women-led agricultural service enterprises. The project also supports institutional strengthening, monitoring, knowledge dissemination and policy dialogue on more competitive domestic rice production.
The project was launched in October 2024 and is financed by a Japan Social Development Fund grant administered by the World Bank. The first World Bank Implementation Status and Results Report was disclosed on 3 September 2026.
Key project information
- Official name
- Sierra Leone Rice Systems Capacity Strengthening Project
- Alternative name
- Strengthening the Rice System in Sierra Leone through South-South Cooperation
- Status
- Active
- Current phase
- Implementation
- Country
- Sierra Leone
- Location
- Four target districts; confirmed demonstration sites include Kambia, Tonkolili and Kenema
- Sector
- Agriculture and food
- Sub-sector
- Agricultural extension, research and support activities
- Project structure
- Recipient-executed Investment Project Financing funded by JSDF and administered by the World Bank
- World Bank project ID
- P180895
- Grant ID
- TF0C6315
- RicherFin project ID
- 06051445-aeee-47f9-bcdc-24dd106ff635
- Estimated cost
- US$2.80 million
- Financing secured
- US$2.80 million
- Approval / launch
- Oct 2024
- Expected completion
- 30 Jun 2027
Financing
The project is financed by a US$2.80 million Japan Social Development Fund grant. The International Bank for Reconstruction and Development and International Development Association administer the funding. The signed agreement allocates the full amount to goods and non-consulting services, consulting services, training, operating costs and institutional-capacity sub-projects.
No financing gap is indicated because the grant equals the stated total project cost. The grant agreement is signed and implementation is active.
- Total project cost
- US$2.80 million
- Financing secured
- US$2.80 million
- Financing gap
- None indicated
- Goods and non-consulting services
- US$1.043 million
- Consulting services
- US$561,500