Overview
The Coastal Resilience and Sustainable Tourism Project, known as WACA+ and identified by the World Bank as P180982, is an Investment Project Financing operation designed to increase the resilience of targeted coastal communities and improve the sustainability of tourism in São Tomé and Príncipe.
The project combines institutional and policy reforms with physical and social investment. Its scope includes coastal adaptation against flooding and erosion, safer settlement areas and social infrastructure, early-warning capabilities, nature-based solutions including mangrove restoration, and investment supporting sustainable tourism destinations and local tourism value chains.
Implementation is active. World Bank financing records show the original IDA financing disbursing with a closing date of 30 June 2029, while the additional IDA financing approved in 2025 is effective. Procurement activity continued into September 2026, including an open works tender covering social housing and school infrastructure in Iô Grande and Praia Abade.
Key project information
- Official name
- Coastal Resilience and Sustainable Tourism Project
- Alternative name
- WACA+
- Status
- Implementation
- Current phase
- Implementation / procurement and civil works
- Country
- São Tomé and Príncipe
- Location
- Targeted coastal communities on São Tomé and Príncipe islands
- Sector
- Environment & Tourism
- Sub-sector
- Coastal resilience · climate adaptation · sustainable tourism · blue economy
- Project structure
- Investment Project Financing (IPF)
- Project ID
- P180982
- Estimated project cost
- US$29.8 million
- Financing secured / identified
- US$24.2 million
- Approval date
- 12 Apr 2024
- Expected completion
- 30 Jun 2029
Financing
WACA+ was originally financed through US$14.4 million of IDA funding, a US$4.0 million PROBLUE trust-fund grant and a documented US$0.2 million private-sector contribution. The original financing package contained a US$5.6 million financing gap.
In 2025, an additional US$5.6 million IDA grant was mobilised through the IDA20 Crisis Response Window. World Bank documentation states that this additional financing was intended to address the project's financing gap and allow full implementation of the planned WACA+ scope without adding new activities.
- Total project cost
- US$29.8 million
- Total financing identified
- US$24.2 million
- IDA financing
- US$20.0 million
- Trust-fund financing
- US$4.0 million
- Private-sector contribution
- US$0.2 million