RicherFin · Sovereign Projects
Mozambique Digital Acceleration Project — Mozambique
Alternative / official name: Mozambique Digital Acceleration Project (MDAP)
Mozambique · Nationwide · Digital infrastructure
Overview
The Mozambique Digital Acceleration Project is a US$200 million national digital-development programme financed by the International Development Association. Approved by the World Bank on 15 July 2022, it aims to increase digital adoption and inclusion while strengthening the foundations for accelerated digital transformation in Mozambique. Financing became effective on 8 November 2022 and the project is scheduled to close on 31 July 2028.
The programme combines broadband expansion with digital inclusion, affordable access to devices, digital skills, connectivity for educational and public institutions, cybersecurity, data protection and improvements to government digital infrastructure. Its four components allocate US$90 million to digital access and inclusion, US$50 million to foundations for accelerated digital transformation, US$10 million to project management and institutional coordination, and US$50 million to contingent emergency response.
Implementation remains under way. The World Bank’s December 2025 report rated progress toward the development objective Moderately Satisfactory and overall implementation Moderately Unsatisfactory. At that date, 36.45% of IDA financing had been disbursed. Procurement continued during 2026, including major rural-broadband and school-connectivity packages.
Key project information
- Official name
- Mozambique Digital Acceleration Project
- Status
- Active — Implementation
- Current phase
- Implementation / procurement
- Country
- Mozambique
- Location
- Nationwide
- Sector
- Digital infrastructure / information and communications technologies
- Project structure
- Investment Project Financing
- World Bank project ID
- P176459
- RicherFin project ID
- 00695f06-bb60-4f00-837d-3edfa98335f6
- Estimated project cost
- US$200 million
- Financing secured
- US$200 million IDA credit at approval
- Approval date
- 15 Jul 2022
- Financing agreement signed
- 26 Aug 2022
- Effectiveness date
- 08 Nov 2022
- Expected completion
- 31 Jul 2028 · Expected
Financing
The project was approved with US$200 million equivalent of IDA financing. The original appraisal documentation describes an Investment Project Financing operation financed through an IDA credit, with no financing gap in the approved structure.
The December 2025 implementation report recorded US$73.10 million disbursed and US$127.44 million undisbursed under IDA-71820, a 36.45% disbursement rate. The revised loan value of US$201.48 million reflected SDR/USD valuation rather than an additional financing commitment.
- Total project cost
- US$200 million
- Financing secured at approval
- US$200 million
- Financing gap at approval
- US$0
- Financing structure
- Investment Project Financing
- Concessional financing
- IDA credit · IDA-71820
Continue to project details